2011 | |
18 July 2011 | Delivery of Helium refrigerator |
13 July 2011 | Finishing production of cable-in-conduit conductor |
5 July 2011 | Start installation of power supply |
2010 |
|
23 Nov 2010 | Purchase order for cryostat (CRIOTEC, IT) |
2 Nov 2010 | Inauguration of HFM Infrastructure Building |
28 Oct 2010 | |
10 June 2010 | Finishing production of 210 km niobium-tin strand for superconducting coil |
19 Feb 2010 | Purchase order for helium-based cooling system (LINDE, CH) |
2009 |
|
30 Nov 2009 | Design packages available for superconducting coil and cryostat |
15 Sep 2009 | Purchase order for 20 kA power supply (IMTECH-VONK, NL) |
17 July 2009 | Installing 250 cubic meter storage tank for cooling water |
17June 2009 | First order for manufacturing cable-in-conduit superconductor |
15 May 2009 | Topping out ceremony for HFM infrastructure building |
9 April 2009 | Cable-in-conduit superconductors tests completed successfully |
2008 |
|
30 May 2008 | Laying of foundation stone for HFM infrastructure building |
11 April 2008 | Purchase order for 210 km niobium-tin wire for superconducting coil |
18 Feb 2008 | Contract signed with utility company Vattenvall on cooling supply for the cooling of resistive coil |
2007 |
|
29 March 2007 | Signing research agreement with National High Magnetic Field Laboratory, Tallahassee (Florida) USA |
28 Feb 2007 | Project approved by German Ministry of Education and Research |
2006 |
|
Nov 2006 | Helmholtz Senate decision on project funds |
27 Oct 2006 | Initiation of planning phase for HFM Infrastructure Building |
2006 | Design drafts on magnet systems in cooperation with NHMFL |