BESSY II resumes operation after a long shutdown

The extensive work during the shutdown was completed on time. A great occasion to celebrate and say thank you to all those involved.

The extensive work during the shutdown was completed on time. A great occasion to celebrate and say thank you to all those involved.

© HZB/V. Mai

On 30 August, BESSY II ligth source will resume user operation: the research centre will then welcome guest researchers from all over the world and support them in their various experiments. The 14-week  shutdown was the longest in BESSY II history. Among other works, the main supply was completely renewed. The successful completion of the work was celebrated with all those involved.

"14 weeks of shutdown - we've never actually had such a long interruption at BESSY II," says Ingo Müller, who coordinated the work during the shutdown with Christian Jung. But there was a lot to do during this time. To ensure a reliable power supply for the storage ring in the future, it was necessary to replace the low-voltage main supply. In addition, new chillers were also installed during the shutdown. They ensure that the air conditioning in the electron storage ring runs reliably.


Read more about the work during the shutdown here.

"Our machine has been running again for almost two weeks now. We are in the middle of commissioning and are doing everything we can to ensure that users will receive the BESSY light beam in the usual quality for their experiments from 30 August onwards," reports Ingo Müller.

The punctual and successful completion of the work was also a reason to celebrate. All the staff involved at HZB and the external companies met on 23 August at BESSY II's forecourt for currywurst & chips - a typical Berlin delicacy!

By the way, BESSY II was a visitor magnet during the shutdown. We were delighted to welcome high-ranking delegations. For example from Singapore, Brasil and Sweden and many visitors at the Long Night of the Sciences.

 

(sz)


You might also be interested in

  • ERC Consolidator Grant for HZB researcher Robert Seidel
    News
    04.03.2024
    ERC Consolidator Grant for HZB researcher Robert Seidel
    Physicist Dr Robert Seidel has been awarded a Consolidator Grant by the European Research Council (ERC). Over the next five years, he will receive a total of two million euros for his research project WATER-X. Seidel will use state-of-the-art X-ray techniques at BESSY II to study nanoparticles in aqueous solution for the photocatalytic production of "green" hydrogen.
  • BESSY II: Molecular orbitals determine stability
    Science Highlight
    07.02.2024
    BESSY II: Molecular orbitals determine stability
    Carboxylic acid dianions (fumarate, maleate and succinate) play a role in coordination chemistry and to some extent also in the biochemistry of body cells. An HZB team at BESSY II has now analysed their electronic structures using RIXS in combination with DFT simulations. The results provide information not only on electronic structures but also on the relative stability of these molecules which can influence an industry's choice of carboxylate dianions, optimizing both the stability and geometry of coordination polymers.
  • BESSY II: Local variations in the structure of High-Entropy Alloys
    Science Highlight
    30.01.2024
    BESSY II: Local variations in the structure of High-Entropy Alloys
    High-entropy alloys can withstand extreme heat and stress, making them suitable for a variety of specific applications. A new study at the X-ray synchrotron radiation source BESSY II has now provided deeper insights into the ordering processes and diffusion phenomena in these materials. The study involved teams from HZB, the Federal Institute for Materials Research and Testing, the University of Latvia and the University of Münster.